Obetsebi Lamptey Interchange Phase II suspended over delayed funds – Engineer

The Chief Resident Engineer of the Obetsebi Lamptey Interchange project, Ing. Owusu Sekeyere Antwi, has disclosed that phase II of the major road project has been suspended due to funding delays caused by outstanding payments owed to the contractor.

Speaking to the media on Saturday, May 3, Ing. Antwi revealed that while only a few works remain to be completed, construction activities have slowed significantly because of resource constraints.

“We are left with a few things to be done, but the contractor has slowed down a little because of resources. In terms of outstanding IPCs, we have over 20 million euros to pay, but the Minister of Finance last year did some payments which were not paid out of the IPCs, so we need to balance all those things to be able to know how much we owe the contractor,” he stated.

His comments come amid growing concern over delays in the delivery of key road infrastructure projects across the country. The Obetsebi Lamptey Interchange is considered a critical link in Accra’s urban road network, expected to ease vehicular congestion in the  Greater Accra Region.

Meanwhile, contractors working on the project have appealed to the government for expedited financial intervention to prevent further disruption.

A parliamentary oversight committee also pledged to engage the relevant ministries to help resolve the bottlenecks and ensure timely completion.

In a related development, Chief Resident Engineer for the Ofankor-Nsawam Road Project, Ing. Kwabena Bempong,  confirmed that the project has also experienced a 15-month delay.

Initially set for completion in July 2024, the road project is now expected to be finalised sometime between mid-2025 and late 2025.

Ing. Bempong attributed the delay to two key challenges, namely the delays in compensating affected residents and difficulties in relocating utility infrastructure along the construction path.

DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of ahantawest.com

Related Posts

Agona Nkwanta Police Arrest Ex-Convict Over Alleged Rape and Murder of 17-Year-Old Girl

The Agona Nkwanta District Police Command has arrested a 45-year-old man, identified as Kudjo Ntow, for his alleged involvement in the rape and murder of Olivia Kwofie, a 17-year-old girl…

OGA DESK Set to Ignite Airwaves as Hon. Mavis Kuukua Bissue Joins King George on OGYA 98.3 FM

Residents of Ahanta West and listeners across the Western Region are in for an engaging and insightful evening as OGYA 98.3 FM presents another exciting edition of OGA DESK, one…

Leave a Reply

You Missed

Agona Nkwanta Police Arrest Ex-Convict Over Alleged Rape and Murder of 17-Year-Old Girl

  • By
  • June 11, 2026
  • 6 views
Agona Nkwanta Police Arrest Ex-Convict Over Alleged Rape and Murder of 17-Year-Old Girl

OGA DESK Set to Ignite Airwaves as Hon. Mavis Kuukua Bissue Joins King George on OGYA 98.3 FM

  • By
  • May 30, 2026
  • 25 views
OGA DESK Set to Ignite Airwaves as Hon. Mavis Kuukua Bissue Joins King George on OGYA 98.3 FM

AHANTAFEST 25 & Annual Music Jam: A Night of Music and Celebration in Ahanta West

  • By
  • December 28, 2025
  • 142 views
AHANTAFEST 25 & Annual Music Jam: A Night of Music and Celebration in Ahanta West

President Mahama directs Finance Ministry to disburse $78m for completion of Takoradi–Agona-Nkwanta road

  • By
  • December 21, 2025
  • 97 views
President Mahama directs Finance Ministry to disburse $78m for completion of Takoradi–Agona-Nkwanta road

Government Declares Three Days of National Mourning for Nana Konadu Agyeman-Rawlings

  • By
  • October 24, 2025
  • 184 views
Government Declares Three Days of National Mourning for Nana Konadu Agyeman-Rawlings

Former First Lady Nana Konadu Agyeman-Rawlings dies aged 76

  • By
  • October 23, 2025
  • 169 views
Former First Lady Nana Konadu Agyeman-Rawlings dies aged 76